The
spare room is where internal work on the house started.
The ceiling here was the only place where there was
'substantial' damage, being a very small hole in the
plaster. The existing internal walls are made of villaboard,
so have very poor strength and insulation. Rather
than remove the villaboard, and have the hassle and
potential of damage to the ceiling when removing the
wall, as well as the potential of asbestos concerns,
we chose to just gyprock a layer over the existing
wall below the picture rail. This added some strength
and insulation. Being an old house, there's currently
no storage, so we also got some built in cupboards
made for this room, doing our best to make them blend
with the room. |
|
|
 |
 |
 |
 |
 |
|
 |
 |
 |
|